英文篇名
Design and Construction of Tunnels Passing Through Faults ~ A Case Study in Xinyi Expressway Project
作者
劉家銘、黃慈銘、彭錦法、周忠仁、曾惠斌
關鍵字
隧道、工程地質、斷層帶、受壓水層、抽坍、支撐、監測。
摘要
信義快速道路工程為銜接北二高萬芳交流道及信義路五段之公路工程,由於以隧道穿越拇指山及象山山區,隧道之工程地質問題為本工程主要需克服之課題。其中成福斷層為本工區主要地質構造,通過本工程文山隧道北上線里程約1K+593至1K+635,南下線里程約1K+563至1K+613, 斷層帶寬度分別約為42及50公尺, 與調查及設計階段預估之斷層位置(1K+555至1K+605)相近。成福斷層帶由破碎之砂岩、頁岩、凝灰岩、及其角礫岩與斷層泥所組成,岩層褶曲破碎,夾多量斷層泥,膠結不良,斷層帶下盤則未出現受壓水層。
本工程遭遇成福斷層段施工對策包括:先進行隧道內水平前進鑽孔探查,以縮短輪進長度及選擇適當支撐形式因應,必要時採固結灌漿強化地盤穩定性,並透過隧道計測系統研判隧道穩定性。依據本工程於成福斷層段及附近路段監測儀器量測結果,數據趨於收斂穩定,無異常變形或持續變形現象,顯示本工程原支撐設計達實際岩體及隧道安全所需。
本工程北上線隧道施工曾遭遇不預期之抽坍事件,經緊急採用頂拱鑽設工字鋼樑加強支撐、灌漿回填及掛網噴凝土封面等處理措施,後續順利通過成福斷層段;南下線成福斷層段之岩性與北上線成福斷層段相近,惟其地層受剪裂褶曲程度較北上線為輕,依據北上線處理之經驗,以縮短輪進長度及採用V類支撐因應,順利通過成福斷層段。茲將本工程通過成福段層帶之抽坍處理及相對應輪進與設計支撐形式經驗分享,期提供後續類似計畫之參考。
英文摘要
Xinyi Expressway is a roadway engineering project that was built to make connections between Wanfang Interchange of National Freeway 3 and Xinyi Road Section 5 of Taipei City. Since it was designed to pass through the Thumb Hill and Elephant Mountain area via tunnels, the tunnel-related engineering geology problems became the main issues of the project.
The major geologic structure within the project is Chenfu Fault, which intercepts the expressway at northbound chainage of about 1K+593 to 1K+635 and southbound 1K+563 to 1K+613 of Wenshan Tunnel with bandwidth of about 42 and 50 m, respectively. The results were compared fairly with the anticipated location (at chainage of about 1K+555 to 1K+605) derived in the investigation and design stage. The fault is composed of fractured sandstone, shale, tuff, and breccia, and fault gouges.
The rock bedding features folding and fracture with abundant weakly-textured fault gorges. There is no confined aquifer discovered in the footwall of the fault.The construction countermeasures against the Chengfu fault in the project included carrying out horizontal drilling exploration in the tunnel, shortening the round length of excavation, and selecting appropriate supporting systems. If necessary, consolidation grouting would be conducted to enhance the ground stability. The stability of the tunnels was further assessed through the monitoring system. According to the measurement obtained from the Chengfu fault section and nearby road sections of the project, the data tended to be converged and no abnormal or continuing deformation was observed, an indicative that the original support design of the project meets the actual safety requirements of the rock mass and tunnel.
During the construction of the northbound tunnel, an unexpected collapse event was encountered at the fault section. After such emergency measures as reinforcement of supporting system by installing steel I-beams on the tunnel crown, back grouting, and shotcrete on the excavation face were applied, the Chengfu fault section was overcame. The lithology of the fault on the southbound is similar to that on the northbound, but the degree of shear folding of the stratum is lighter.
Based on the northbound experience, the Chengfu fault section of southbound tunnel was successfully conquered by shortening the round length and adopting V-class supports. This paper shares the experience obtained from the collapse treatment of the Chengfu fault section and the corresponding round length and design supports. It is hoped to provide a reference for similar projects in the future.